NEWCOMBE ROAD SAND

Timeline

Stevenson has a long-standing history, helping to build New Zealand’s largest city’s rail, transport connections and homes. Newcombe Road Sand will play a vital role in the BOP region’s future.
2017

Waipa 2050 Growth Strategy completed.

Mid 2019

Agreement for land access and use between Whitehall Fruitpackers Holdings Ltd and RS Sand Ltd.

2020-21

Resource testing, site selection and quarry design undertaken.

2021-22

Resource consent assessments undertaken.

2022

Waipa Transport Strategy completed.

Jan 2023

Stevenson Aggregates purchases Revital’s shares in RS Sand.

May 2023

RS Sand submits land use resource consent application for Newcombe Road Sand

June 2023

Request for further information (Section 92) from district and regional councils.

If consent approved:

YEAR 1

Planned (if consent granted) start of construction of infrastructure and quarry.

YEAR 1-2

Planned development of wetlands and native forest along Karipiro Stream.

YEAR 2-3

Planned completion of Stage 1 of quarrying, rehabilitation and return to grazing.

YEAR 3-7

Planned completion of Stage 2 of quarrying, rehabilitation and return to grazing.

YEAR 7-15

Planned completion of Stage 3 of quarrying, rehabilitation and return to grazing.

YEAR 20

Planned completion of Stage 4 of quarrying, rehabilitation and return to grazing.

YEAR 25

Planned completion of quarrying, rehabilitation of entire site and disestablishment of sand quarry.